6 questions Intermediate

ECADEMY test

32 - Industrial Water Treatment

This course test contains 6 questions and can be retaken at any time.

You must answer all questions correctly to pass the test and complete the course.

Start test

Question 6 of 6 Intermediate

Happy with your answers?

Submit your current answers and get the final test result.

Submit

Test results

Congratulations. You have passed the test and completed the 32 - Industrial Water Treatment

Achieved badges:

How would you rate this course?

You are welcome to add your rating of this course. Remember that you have to be logged in before you take the test to be able to give your rating.

Continue training Go to MyECADEMY

Sorry. You did not pass the 32 - Industrial Water Treatment test this time

How would you rate this course?

You are welcome to add your rating of this course. Remember that you have to be logged in before you take the test to be able to give your rating.

Correct
Q: What is the problem of using throttling valves to decrease flow on a fixed speed pump?
A: It wastes large amounts of energy and money
Correct
Q: How small particles can an ultrafiltration plant remove?
A: Down to 0,010 µm
Correct
Q: In addition to process water, industries have another type of water that needs treatment. Which?
A: Wastewater
Correct
Q: What is the main purpose of balancing water?
A: To avoid corrosion in the pipes or of other materials used elsewhere in the process
Correct
Q: What is aeration?
A: A process that brings oxygen into the water to get rid of volatile components
Correct
Q: Why is it a good idea to choose pumps with integrated drives?
A: It can help reduce the motor size, optimise performance and protect the pump